Coral Hills Drive Improvement

Print
Coral Hills Drive Road Work

WORK IS SCHEDULED TO BEGIN ON:

January 16, 2017

Until Approximately Mid-February

During this time, no northbound traffic will be permitted along Coral Hills Drive, between 31st Court and Sample Road. The contractor will return during the summer, to mill and resurface Coral Hills Drive.

The City of Coral Springs is taking proactive steps to replace the City’s aging
infrastructure to prevent costly sewer and water line breaks.
Download Flyer

As part of an investment in the City’s downtown area, a new water main is being installed on Coral Hills Drive. The project is part of the city’s downtown water and sewer improvements that entails removing pipes more than 50 years old and replacing them with large-capacity water and sewer mains to prepare for a growing and revitalized downtown.

Questions:
Contact Public Information
Officer Angel Gardner
954-410-8363
Angel.Gardner@qcausa.com


Street Closing - 94th Ave - 31st Ct. to Sample Rd.

Over the next week, 6-8 weeks, portion of 94th Ave will be closed for Utility installation.

Phase 1: Starting 1/16/17, 94th Ave. from 31st Ct. North to 32nd St. will be closed for approx. 2 weeks. (one access to the Post Office will be open at all times.)

Phase 2: The intersection at 94th Ave. and 32nd St. will be closed.

Phase 3: 94th Ave. from 32nd St. North to Sample Rd. will be closed.


Scope:
The contractor, R.P. Utility & Excavation Corp., will replace the water main on Coral Hills Drive from Sample Road to Northwest 31st Court.

During construction, the contractor will close the northbound lane between Sample Road and Northwest 31st Court from 7 a.m. to 5 p.m. Monday through Friday.

Traffic will be open in both directions in the evening. Driveways may be temporarily blocked during water main installation.

This will limit some access to residences and parking for a brief period. Advance notice will be provided before this occurs.

Detours:
Northbound traffic will be detoured at Northwest 31st Court.